Possession and Handover Checklist: How to Inspect Your New Flat for Snags

13 min readUpdated 5 November 2026
Possession and Handover Checklist: How to Inspect Your New Flat for Snags
Table of contents
  1. 1.1. Separate a possession offer from a completed handover
  2. 2.2. Check the occupation documents for your actual tower
  3. 3.3. Arrange a properly supported inspection appointment
  4. 4.4. Establish a room-by-room evidence trail
  5. 5.5. Look carefully at walls, ceilings and moisture
  6. 6.6. Inspect floors, tiles and bathroom drainage
  7. 7.7. Test plumbing and sanitary fixtures under normal use
  8. 8.8. Have electrical safety checked by a qualified person
  9. 9.9. Operate doors, windows and balcony fittings
  10. 10.10. Match the kitchen and supplied equipment to the contract
  11. 11.11. Check dimensions and parking without confusing area definitions
  12. 12.12. Extend the review beyond the apartment door
  13. 13.13. Reconcile the final account and handover pack
  14. 14.14. Agree priorities, repair dates and a genuine reinspection
  15. 15.15. Understand defect liability and preserve your remedies
  16. 16.16. Plan the move-in and speak to Reality Choice
  17. 17.Frequently asked

A possession invitation is the start of a verification process, not proof that every part of your home is ready. Use this practical checklist to inspect documents, finishes, services and shared facilities, record defects clearly and agree a written rectification plan before moving into your new flat.

1. Separate a possession offer from a completed handover

Receiving a possession letter is exciting, especially after years of rent and loan payments. However, a demand for the final instalment, permission to carry out interiors, physical delivery of keys and lawful occupation are different events. Identify exactly what the developer is offering and which contractual obligations each event triggers. A fit-out invitation should not be treated as confirmation that a building is authorised for residential occupation. Start with your agreement for sale, allotment papers, specifications and previous correspondence. Make a folder of promised fixtures, payment receipts, approved variations and the possession notice. Write down the response deadline and any stated start date for maintenance or holding charges. If documents or essential services are missing, raise a dated written query promptly rather than simply ignoring the notice. A lawyer can assess disputed deadlines and payment obligations; a snag inspector cannot decide those legal questions for you.

2. Check the occupation documents for your actual tower

Ask for the applicable Occupation Certificate or occupancy approval issued by the competent authority, together with enough information to verify it independently. Check the project name, site address, tower, floors and any conditions or exclusions. A certificate for another tower or a limited completed portion does not automatically cover your apartment. Where completion and occupation documents are separate, ask which have been issued and which remain pending. Cross-check project disclosures with the relevant Haryana RERA record for a Gurugram purchase. Obtain applicable fire approvals, lift commissioning records and utility connection information from the developer. An electricity meter or an active lift is not a substitute for occupation permission. Conversely, an occupation certificate does not certify that every tile, tap or cupboard in your particular flat is defect-free. Legal document review and physical snagging answer different questions, and a careful buyer needs both before treating handover as complete.

3. Arrange a properly supported inspection appointment

Book a daylight appointment with access to every room, balcony, utility area and allotted parking space. Ask the handover team to ensure water, electricity and relevant equipment are available for safe testing. Request access to shared facilities through authorised staff. If supply is temporary or a system cannot be operated, mark the item untested rather than passing it by assumption. Arrange a second visit when that system is available. Carry your specifications, a printed checklist, phone charger, torch, tape measure, notebook and removable marking labels if permitted. Bring someone who can take notes while you inspect. An independent building inspector can help identify defects, while qualified electricians, plumbers or structural engineers should handle specialist concerns. Do not let an inspection become an unsafe experiment: buyers should not open electrical panels, enter shafts, climb parapets or test fire equipment without authorised professionals. Ask about the inspector's scope, exclusions and reporting format before engaging them.

4. Establish a room-by-room evidence trail

Inspect systematically, starting at the entrance and moving through the flat in the same order on every visit. Give each defect a unique reference, room name, exact location and short factual description. For example, an illustrative entry might read: kitchen, below sink, water dripping at waste-pipe joint during tap use. This is more useful than a general complaint that plumbing is poor. Take a wider photograph to establish location and a close-up showing the defect. Add a video where movement, noise or leakage cannot be explained well in a still image. Retain original dated files and share a numbered report through a traceable channel. Distinguish between what you observed and what requires professional diagnosis. A crack may need assessment, but a photograph alone rarely establishes its structural significance. Ask the developer's representative to acknowledge receipt; an acknowledgment records the issue without requiring you to accept their proposed explanation.

5. Look carefully at walls, ceilings and moisture

Examine walls and ceilings in natural light, including corners, window edges, service ducts and areas adjoining bathrooms. Look for damp patches, bubbling paint, salt deposits, staining, uneven plaster and visible cracks. Photograph the location before any repainting. A freshly finished surface can hide an unresolved moisture source, so ask how the underlying problem will be diagnosed rather than agreeing immediately to cosmetic touch-ups. Note whether a patch appears after water use, rain or air-conditioning operation, but do not claim certainty about the cause without investigation. Cracks accompanied by unusual movement, exposed reinforcement or other concerning signs should be assessed by a qualified engineer. Never accept a salesperson's blanket assurance that all cracks are harmless settlement. Equally, do not describe every hairline finish crack as structural failure. Request a written repair method, responsibility for associated finishes and an observation period where appropriate to the defect.

6. Inspect floors, tiles and bathroom drainage

Walk through every room and examine tiles or other flooring for visible cracks, chips, uneven joints and sharp level differences. Look at thresholds and transitions between materials. Any gentle tapping or technical assessment of bonding should be agreed with the developer and performed appropriately; a sound difference alone is not a complete diagnosis of installation quality. Record the precise affected area rather than demanding replacement of an entire floor without evidence. With authorised assistance, run water in wet areas and observe whether it reaches the drain without persistent unwanted pooling or escape into adjoining dry rooms. Avoid uncontrolled flooding or prolonged ponding tests, which can damage finishes or neighbouring flats. Such tests require a planned method and professional supervision. Check drain grates, accessible traps and finished floor levels around shower partitions. Ask how a repair will protect waterproofing, because replacing a tile carelessly can create a new leakage problem.

7. Test plumbing and sanitary fixtures under normal use

Operate each tap, mixer, shower and flush where water is available. Observe flow, visible leakage, fixture stability and drainage during normal use. Open the cabinet below the kitchen sink and check accessible joints while water runs. Look around washbasin traps, toilet bases and washing-machine connection points. Confirm that promised hot and cold water provisions are correctly identified and that any supplied appliance can be demonstrated safely. Ask staff to identify the main water isolation valve and explain how to shut off supply during a leak. Confirm accessible service points without dismantling concealed pipework yourself. Low pressure or intermittent supply may arise from a temporary commissioning arrangement, but it still needs a recorded follow-up and retest. Do not allow an untested bathroom to disappear from the report because the building's water system was unavailable on inspection day. A completed checklist should identify evidence, exceptions and outstanding tests, not merely a row of ticks.

8. Have electrical safety checked by a qualified person

Check visible switch plates, sockets, light points and supplied fittings against the agreed specifications. Look for loose mounting, broken covers, exposed wiring and signs of overheating. A qualified electrician should verify relevant protective devices, earthing and circuit behaviour with suitable instruments. A phone charger can demonstrate that a socket supplies power, but it cannot establish that the installation is safe or properly earthed. Ask for the distribution-board circuit labels and a demonstration of normal isolation procedures. Confirm the sanctioned load, meter identification, billing arrangement and backup supply provisions, including which circuits receive backup and how usage is charged. Do not assume an advertised backup facility operates every appliance in the flat. If a safety concern appears, stop testing the affected circuit and request professional attention. Keep commissioning reports and warranties where provided, and ask the developer to record what was tested rather than offering only a verbal statement that electrical work is complete.

9. Operate doors, windows and balcony fittings

Open and close every door and window, including balcony sliders and service-area shutters. Check alignment, handles, locks, latches, hinges, seals and visible glazing damage. A door that scrapes the floor or a window that will not latch should be recorded even if the representative says adjustment is routine. Test operation normally; forceful handling can cause damage and create an avoidable dispute about responsibility. Inspect external-facing joints for obvious gaps and ask about the approved procedure for investigating suspected rainwater ingress. Do not spray large quantities of water onto façades without permission and supervision. Look at balcony drainage, railing stability and visible corrosion from a safe position. Never lean heavily on an uncertain railing to prove it is secure. Missing barriers, loose glazing or unsafe balcony conditions are urgent safety issues, not minor finishing snags to be deferred until after a family has moved in.

10. Match the kitchen and supplied equipment to the contract

Compare installed cabinetry, counters, sinks and appliances with the specification schedule and any signed substitutions. Open drawers and shutters, check accessible edges and examine countertop joints. Look for swelling, damaged laminates, misaligned doors and unsealed openings around plumbing. Confirm that service access remains practical after cabinetry installation. A neat appearance should not hide a valve or connection that maintenance staff cannot reach when something fails. For supplied appliances, record brand, model and serial number, collect manuals and understand warranty activation. Ask for an authorised commissioning demonstration where required. Do not operate equipment without the necessary supply or ventilation. Clarify whether exhaust provision includes an installed duct and functional outlet or only an opening for future installation. Where a promised product has been changed, obtain the contractual basis and written explanation; describing a replacement as equivalent does not by itself resolve a disagreement about agreed specifications.

11. Check dimensions and parking without confusing area definitions

Use measurements as a screening tool and compare like with like. Carpet area, balcony area, built-up area and saleable area are not interchangeable labels. A buyer's approximate wall-to-wall measurements may flag a discrepancy, but they are not automatically a professional area certificate. If the difference appears significant, ask for the approved plan, contractual area statement and a qualified survey or architectural review. Visit the actual parking location identified in your documents. Check bay markings, vehicle access, turning clearance, height restrictions and whether the space is obstructed by services or columns. Clarify the legal nature of your parking entitlement through the agreement and applicable law rather than assuming that any painted bay is separately owned property. If mechanical parking is involved, obtain operating restrictions and a demonstration from authorised staff. Record whether your normal vehicle can use the allotted arrangement safely, subject to the system's published limits.

12. Extend the review beyond the apartment door

Look at corridors, staircases, entrance access, lighting and visible emergency routes. Ask authorised staff about lift operation, emergency communication and rescue procedures. Do not activate alarms, disable access controls or interfere with fire systems during a buyer visit. Where fire doors, escape routes or lift facilities appear unsafe, document the concern and request attention from the responsible technical team before occupancy. Compare the delivered common facilities with the agreement and disclosed phase schedule. A clubhouse in a later phase is different from an operational facility in your handed-over tower. Ask which amenities are available now, which remain under construction and what contractual completion commitments apply. Check waste collection, water arrangements, security procedures and access for emergency vehicles. Individual snagging cannot replace an association's technical audit of a whole development, but it can reveal important issues that should be escalated collectively and recorded before residents become dependent on incomplete services.

13. Reconcile the final account and handover pack

Request an itemised final statement distinguishing the balance purchase price, applicable taxes, deposits, maintenance advance, meter charges and other contractual amounts. Match each item to the agreement, receipts and relevant demand. Ask for an explanation of disputed additions and seek legal advice before withholding a payment that may be contractually due. A defect report and a payment dispute should be documented clearly rather than blurred into an informal argument at the handover desk. Collect keys, access cards, meter readings, utility account details, warranties, manuals and emergency contacts. Record the number of keys and the opening readings in a signed inventory. Clarify the maintenance commencement date, billing basis, deposit treatment and responsible facility manager. Ask when conveyance or registration is due and what documents remain outstanding. Keep copies securely in more than one location. A thick handover folder is useful only if its contents correspond to your flat and can be understood later.

14. Agree priorities, repair dates and a genuine reinspection

Separate urgent safety or habitability concerns from functional defects and cosmetic finishing items. An illustrative classification would put exposed live wiring above a stiff drawer, while both remain recorded. Ask the developer to identify a responsible person, proposed action and target date for every unresolved item. Avoid signing a blanket statement that everything is satisfactory when the report says otherwise. If accepting keys with reservations, have a lawyer review wording where rights or deadlines may be affected. Reinspect repaired items under the same conditions that revealed the original issue. A painted ceiling is not proof that a leakage source has been fixed. Check surrounding finishes for repair damage and keep before-and-after evidence. Close individual items only after verification, recording any residual concern. Do not sign an undated closure form or allow an overall completion signature to substitute for testing systems that were unavailable during the first inspection.

15. Understand defect liability and preserve your remedies

Section 14(3) of the Real Estate (Regulation and Development) Act addresses structural defects and other specified defects in workmanship, quality, services or promoter obligations under the agreement. Where covered defects are brought to the promoter's notice within five years from handing over possession, the provision requires rectification without further charge within thirty days, with compensation consequences for failure as provided by the Act. Coverage and relief in an individual dispute require examination of the facts and applicable proceedings. Report problems promptly in writing rather than waiting until the end of that period. Keep proof of delivery, photographs, inspection reports and repair correspondence. Normal wear, owner alterations and damage caused by third-party contractors can raise different issues; preserve evidence before interiors begin. If the promoter does not respond, obtain advice on the appropriate RERA or other available forum and procedural requirements. Do not assume that a verbal promise, an association complaint or negotiations automatically protect every limitation deadline.

16. Plan the move-in and speak to Reality Choice

Before moving furniture, confirm that essential safety concerns are resolved, occupation documentation is appropriate and everyday services work. Protect finished surfaces during interiors and ensure contractors follow building rules. Make a baseline photographic record before third-party work starts so later damage can be distinguished from original defects. Keep the snag report open for clearly identified outstanding items rather than assuming the move-in date ends all follow-up. For help organising property comparisons and the questions to ask during a Gurugram or Delhi NCR handover, contact Reality Choice on +91 8586810942 by call or WhatsApp. Ask what support is available for your transaction and engage independent qualified specialists for technical certification or legal opinions. This guide provides general information, not legal or tax advice, and is not a structural or electrical safety certification. Project documents, competent-authority requirements and professional advice should guide decisions on occupation, payments and dispute resolution.

Sources and verification

Developer materials describe the project; confirm current availability, construction status and your unit’s terms separately.

Frequently asked

Should I inspect a flat before taking the keys?
Arrange a documented inspection before final acceptance where access permits. Key delivery, payment deadlines and legal possession may have different consequences, so obtain advice on the agreement rather than assuming an inspection automatically suspends your obligations.
Does an occupation certificate mean there are no snags?
No. Verify that the approval covers your tower and unit, but separately inspect the flat's finishes, fixtures and services. Occupation permission does not replace a room-by-room defect inspection.
Can I test electrical safety with a phone charger?
A charger only indicates that power is available at that point. Earthing, protective devices and wiring safety require suitable tests by a qualified electrician. Do not open panels or touch exposed conductors yourself.
How should I report seepage?
Identify the room and exact location, photograph the patch, note when it appears and send a written report. Ask for diagnosis and repair of the source, not only repainting, followed by an appropriate reinspection.
What does RERA say about defects after possession?
Section 14(3) provides a five-year notification window from handover for covered defects and requires rectification within thirty days without further charge. The scope and appropriate remedy depend on the defect, evidence and applicable proceedings.
Can I withhold the whole final payment until every snag is fixed?
Do not assume that you can. Payment and possession obligations depend on the agreement and applicable law. Record defects, dispute unsupported charges in writing and obtain a lawyer's advice before withholding an amount or signing acceptance documents.